[vc_row gap=”30″][vc_column][/vc_column][/vc_row][vc_row][vc_column][vc_text_separator title=”POWER PLANTS” i_type=”material” i_icon_material=”vc-material vc-material-dehaze” i_color=”black” i_size=”sm” title_align=”separator_align_left” color=”black” add_icon=”true”][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_column_text]

E.Ü.A.Ş. Orhaneli Thermal Power Station

Renewal of metal sheets of hot & cold gas ducts; maintenances of soot blowing equipment, steam valves and gas canal throttles; replacement of luvo bunkers and ash conveyance pipes with newly produced basalt pipes; replacement of luvo seal metal sheets; renewal of electro filter entrance deceleration plates, redirecting metal sheets, wall sheets and profiles.

Rehabilitation of 210MW Main Boiler SHT1, SHT2 and ECO1 Boiler; Boiler pipe disassembly, assembly and renewal of various isolations belonging to main boiler.

Disassembling of luvo combs and assembling of new ones; renewal of metal sheets of silencer and gas duct.

Applying new coating with Ulpolen1000 (UMHW-PE) material on failed and deformed parts of coal bunkers and lime stone bunkers.

Replacement of boiler hanger and RHT2 pipes as a package, replacement of screen tubes and welding works; sandblasting, pinning and coating of hopper area pipes and coating hopper area pipes with SiC refractor mixture.

Replacement of boiler hanger pipes, SHT1, SHT3, RHT2 pipes, pawls and clamps; renewal of economizer elbows and welding works.

Replacement of metal sheets and isolation of condensate boiler.[/vc_column_text][/vc_column][vc_column width=”1/2″][vc_gallery interval=”3″ images=”171,170,169″ img_size=”full”][/vc_column][/vc_row][vc_row][vc_column][vc_separator border_width=”5″][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_column_text]

E.Ü.A.Ş. Tunçbilek Thermal Power Station – Kütahya

Renewal, disassembly and assembly of 1st Unit Reheater and 2nd Reheater package pipes and collector pipes.

TIG welding of top and bottom panel of 1st and 2nd Unit’s Heater Packages; rehabilitation, disassembly and assembly of package pipes, streamer pipes, EKO and re-heater elbows.[/vc_column_text][/vc_column][vc_column width=”1/2″][vc_gallery type=”flexslider_slide” interval=”3″ images=”191,193,194,195,196,197,198,199,200,201,202″ img_size=”full” onclick=””][/vc_column][/vc_row][vc_row][vc_column][vc_separator border_width=”5″][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_column_text]

E.Ü.A.Ş. Seyitömer Thermal Power Station – Kütahya

Total 24.000 meters of boiler pipe replacement in 2nd and 3rd Unit; replacement of luvo seal metal sheets; disassembly and assembly of 1st Unit hot gas canal refractor; manufacturing and rehabilitation of platform and isolation.[/vc_column_text][/vc_column][vc_column width=”1/2″][/vc_column][/vc_row][vc_row][vc_column][vc_separator border_width=”5″][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_column_text]

Çelikler Holding Seyitömer Thermal Power Station – Kütahya

Disassembly and assembly of 6 Hot Gas Canals Refractors in 1st and 3rd Unit.[/vc_column_text][/vc_column][vc_column width=”1/2″][/vc_column][/vc_row][vc_row][vc_column][vc_separator border_width=”5″][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_column_text]

S.E.A.Ş. Soma Thermal Power Station – Manisa

Disassembly and assembly of 1st and 4th Unit’s boiler bottom band gallery.

Manufacturing, assembling and activating of cinder tray of Unit boiler.[/vc_column_text][/vc_column][vc_column width=”1/2″][vc_gallery type=”flexslider_slide” interval=”3″ images=”203,204″ img_size=”full” onclick=””][/vc_column][/vc_row][vc_row][vc_column][vc_separator border_width=”5″][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_column_text]

Y.E.A.Ş. Yatağan Thermal Power Station – Muğla

Coating of metal sheets in top and bottom coal burners in 2nd and 3rd Unit boilers; renewal of separator outrun, redirector and dust coal canals.

Maintenance & repair and renewal of 18 mill throat movement propulsion systems.

Luvo revision of Unit B.

Luvo revisions of Unit A and B.

Pipe and elbow replacements and armoring of Unit boiler EKO area.

Within unit revision, armoring of RHT2 pipes, RHT3 pipe replacements and inflection, assembling and welding of SHT1 elbows.

Replacement of corroded metal sheets in Unit interior electrofilter gas ways, renewal of compensators; renewal, maintenance and repair of redirectors, ash catchers and flaps.

Replacement of Unit EKO area elbows.

Replacement of Unit SHT2  collector room elbows.

Replacement and armoring of Unit EKO area package elbows.[/vc_column_text][/vc_column][vc_column width=”1/2″][vc_gallery type=”flexslider_slide” interval=”3″ images=”205,206,207,208,209,210,211″ img_size=”full” onclick=””][/vc_column][/vc_row][vc_row][vc_column][vc_separator border_width=”5″][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_column_text]

K.E.A.Ş. Kemerköy Thermal Power Station – Muğla

Setting up AR washing line on exhaust gas desulphurization system and PLC automation (TÜBİTAK MAM Project).[/vc_column_text][/vc_column][vc_column width=”1/2″][vc_gallery type=”flexslider_slide” interval=”3″ images=”212,213,214,215″ img_size=”full” onclick=””][/vc_column][/vc_row][vc_row][vc_column][vc_separator border_width=”5″][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_column_text]

E.Ü.A.Ş. Sarıyar Hasan Polatkan Hydroelectric Power Plant – Ankara

Maintenance and operation of hydroelectric power plant.[/vc_column_text][/vc_column][vc_column width=”1/2″][/vc_column][/vc_row][vc_row][vc_column][vc_separator border_width=”5″][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_column_text]

E.Ü.A.Ş. Afşin Elbistan Thermal Power Station – Kahramanmaraş

Repair of burst boiler pipes, replacement of valves; maintenances of mill outruns, burden lines and steamed soot blowers in 2nd, 3rd and 4th Units.

Pipe manufacturing, disassembly and assembly of the big boiler.[/vc_column_text][/vc_column][vc_column width=”1/2″][/vc_column][/vc_row][vc_row][vc_column][vc_separator border_width=”5″][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_column_text]

E.Ü.A.Ş. Kangal Thermal Power Station – Sivas (Konya Şeker Torku)

Supplying, disassembly and assembly of unit ash conveyance compressors and basalt coated ash conveyance lines.[/vc_column_text][/vc_column][vc_column width=”1/2″][/vc_column][/vc_row][vc_row][vc_column][vc_separator border_width=”5″][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_column_text]

E.Ü.A.Ş. Ambarlı Natural Gas Combined Cycle Power Plant – İstanbul

Disassembly and assembly of 90,000 meters of finned tubes of Number 31 heat recovery steam generator’s YB EKO1, YB EKO2, AB EVA, AB EKO and Condensate Heater; repair or replacement of various metal sheet cracks and renewal of insulations.

Disassembly and assembly of 110,000 meters of finned tubes of AB EKO, YB EKO1, YB EKO2 and Condensate Heaters of Number 11 and 12 heat recovery steam generators; repair or replacement of various metal sheet cracks of boiler walls; renewal of insulations and revision of K1, K2 dampers (208 clacks in total).[/vc_column_text][/vc_column][vc_column width=”1/2″][vc_gallery interval=”3″ images=”216″ img_size=”full”][/vc_column][/vc_row][vc_row][vc_column][vc_separator border_width=”5″][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_column_text]

E.Ü.A.Ş. 18 Mart Çan Thermal Power Station –  Çanakkale

Disassembly and assembly of pipes on 2nd Unit boiler’s coal ways; disassembly and assembly of metal sheet and refractor.

Dismantling and chemical cleaning of evaporative cooler panels and assembling of panels to the exact places completely.[/vc_column_text][/vc_column][vc_column width=”1/2″][vc_gallery interval=”3″ images=”217,218,219,220,221,222,223″ img_size=”full”][/vc_column][/vc_row][vc_row][vc_column][vc_text_separator title=”SUGAR REFINERIES IN TURKEY” i_type=”material” i_icon_material=”vc-material vc-material-dehaze” i_color=”black” i_size=”sm” title_align=”separator_align_left” color=”black” add_icon=”true”][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_column_text]

Ankara Sugar Refinery

Manufacturing, disassembly and assembly of steam generator, collector and panel pipes.[/vc_column_text][/vc_column][vc_column width=”1/2″][/vc_column][/vc_row][vc_row][vc_column][vc_separator border_width=”5″][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_column_text]

Ankara Makina Fabrikası (Ankara Machine Plant)

Boiler panel pipe manufacturing and welding, manufacturing and assembling of these with pipe TIG welding method.

Manufacturing of eko pipes and superheater serpentine pipes of steam generator.

Manufacturing of warehouse, boiler, cement mill, helix, diffusion, scalding trough parts and steam generator gas channel.

Disassembly and assembly of gas flues of lime kilns and manufacturing of inter-connection components.

Welding and manufacturing of screen tubes and collectors of 50 t/h boiler, using TIG welding method.[/vc_column_text][/vc_column][vc_column width=”1/2″][vc_gallery interval=”3″ images=”224,225,226,227″ img_size=”full”][/vc_column][/vc_row][vc_row][vc_column][vc_separator border_width=”5″][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_column_text]

Afyon Sugar Refinery

Disassembly and assembly of superheater II pipe of 100 t/h Steam generator and replacement of coal dust path and cooling water line.[/vc_column_text][/vc_column][vc_column width=”1/2″][/vc_column][/vc_row][vc_row][vc_column][vc_separator border_width=”5″][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_column_text]

Eskişehir Machine Plant

Steel construction manufacturing of beet dumping machine.

Maintenance and repair works of mechanical and electrical establishments.[/vc_column_text][/vc_column][vc_column width=”1/2″][/vc_column][/vc_row][vc_row][vc_column][vc_separator border_width=”5″][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_column_text]

Çorum Sugar Refinery

Replacement of boiler pipe.[/vc_column_text][/vc_column][vc_column width=”1/2″][/vc_column][/vc_row][vc_row][vc_column][vc_separator border_width=”5″][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_column_text]

Susurluk Sugar Refinery

Disassembly and assembly of 5o t/h steam generator pipes and welding works of various spots.[/vc_column_text][/vc_column][vc_column width=”1/2″][/vc_column][/vc_row][vc_row][vc_column][vc_separator border_width=”5″][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_column_text]

Ilgın Sugar Refinery

Disassembly and assembly of boiler dust cyclones; welding, metal sheet coating and renewal of insulation.

Disassembly and assembly of various sized pipes boiler pipes and various welding works with TIG welding method.[/vc_column_text][/vc_column][vc_column width=”1/2″][/vc_column][/vc_row][vc_row][vc_column][vc_text_separator title=”T.C. GENERAL DIRECTORATE OF HIGHWAYS (T.C. KARAYOLLARI GENEL MÜDÜRLÜĞÜ)” i_type=”material” i_icon_material=”vc-material vc-material-dehaze” i_color=”black” i_size=”sm” title_align=”separator_align_left” color=”black” add_icon=”true”][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_column_text]

7th District Office – Samsun

Electronic system maintenance of Tunnel Maintenance and Management Directorate.[/vc_column_text][/vc_column][vc_column width=”1/2″][/vc_column][/vc_row][vc_row][vc_column][vc_separator border_width=”5″][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_column_text]

Highways Workplace Directorate – Ankara

Maintenance and repair works.[/vc_column_text][/vc_column][vc_column width=”1/2″][/vc_column][/vc_row][vc_row][vc_column][vc_separator border_width=”5″][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_column_text]

4th District Directorate – Ankara

Maintenance and repair works.[/vc_column_text][/vc_column][vc_column width=”1/2″][/vc_column][/vc_row][vc_row][vc_column][vc_text_separator title=”TURKISH COAL ENTERPRISE ” i_type=”material” i_icon_material=”vc-material vc-material-dehaze” i_color=”black” i_size=”sm” title_align=”separator_align_left” color=”black” add_icon=”true”][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_column_text]T.C.D.D.

Concrete Sleepers Plant Directorate – Sivas

Replacement and sandblasting of interior and base metal sheets of 3 silos that have 324 tonnes capacity.

Renewal of internal partitions of 3 aggregate silos with 324 tonnes capacity.[/vc_column_text][/vc_column][vc_column width=”1/2″][/vc_column][/vc_row][vc_row][vc_column][vc_text_separator title=”OVERSEAS SERVICES” i_type=”material” i_icon_material=”vc-material vc-material-dehaze” i_color=”black” i_size=”sm” title_align=”separator_align_left” color=”black” add_icon=”true”][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_column_text]

Bulgaria

Devnia Sugar Plant

Manufacturing and assembly of 500 ton/h sugar drying trommel.[/vc_column_text][/vc_column][vc_column width=”1/2″][/vc_column][/vc_row][vc_row][vc_column][vc_separator border_width=”5″][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_column_text]

      Irak

        Süleymaniye Tasluce Cement Plant
  • Disassembly and assembly of rotary mantle mill.

[/vc_column_text][/vc_column][vc_column width=”1/2″][/vc_column][/vc_row]